From about January 2001, the Russian Federation Navy and the
to comply with the promise of President Putin to the relatives of the crew. The first consortium formed, Smit-Heerema-Halliburton, withdrew because Halliburton believed the end of the year recovery deadline could not be safely achieved. In mid May 2001, the Russian Federation and RUBIN, jointly contracted Mammoet-Smit (M-S) to recover the
The M-S strategy was to effect the recovery in three phases, these being:
Phase 1: Preparatory activities, including surveying, radiation monitoring of the submarine, removal of silt around the area of the intended hull cutting operation, and cutting of the hull just forward of the № 1 bulkhead to sever the most damaged part of the submarine. Then, to give a stable and predictable lift and to mount the rigs, to cut 26 holes through the casing and pressure hull either side of the vertical centerline of the main hull for the subsequent insertion and clamping of the lifting fittings. The positions of these holes were selected by the RF to minimize hull bending during the lift and none were positioned in the reactor compartment. This also included the modification of the
Phase 2: Installation of the 26 lifting fittings, the lowering through the pre-inserted tubes in the barge hull and connecting of 26 sets of lifting cables, each comprising 54 strands of seven twisted wires each 6mm diameter and the raising of the
Phase 3: The fitting of two large pontoons, one under each side of the barge, to lift it entirely out of the water to give sufficient clearance of the underslung
Severing the remains of № 1 compartment deployed a heavy cable carrying thick-walled tubular sections coated with a very coarse (~25mm) abrasive. Reciprocating motion was to be provided by two 30 tonne hydraulic rams attached by suction anchors to the seabed.
The strand jack system relies on two collets on each strand, the upper collets being hydraulically lifted/lowered as a cable group. Additional hydraulics activate the collets under computer control, the timing of the collet activation determining whether the strands are raised or lowered. Each cable lifting system was to be supported by four pneumatic cylinders with 4m strokes and with a large nitrogen gas reservoir, the pressure being matched to the cable load so that large movements due to swell (within the cylinder stroke limits) would have minimal effect on the cable loads.
NUCLEAR & RADIOLOGICAL SAFETY
In early June, Large & Associates were engaged by M-S to complete a preliminary assessment of the nuclear hazard and held a number of meetings with RUBIN to discuss and determine the information and data likely to be made available from the RF authorities with respect to radiation and nuclear safety issues. On the basis of this information, Large & Associates was instructed to form and head up the Nuclear Coordinating Group (NCG).